Diyí dzínisà gújá nágúdīgòy (Good morning),
Please see the attached on behalf of Enmax.
Copy of Address list for delivery _Outage and Construction Notice
Notice Distribution Request:
Please see the attached combined construction and outage notice, address list of properties impacted by both the planned outage and construction, and the details below:
Project construction details:
Reference: 21826597
Date: September 14, 2026.
Location: Weaselhead Road and Bullhead Road
Duration: Approximately three (3) weeks
Work times: Weekdays 7 a.m. – 5 p.m. Some weekend work may be required
Project outage details:
Reference: 39607
Date: September 24, 2026
Duration: 7 Hours
Work times: 8 a.m. – 3 p.m.
Note: Addresses impacted by a power outage will receive a separate notification outlining important outage information
ENMAX Power kindly seeks your support to relay this project information to any impacted Tsuut’ina Nation departments for awareness. We greatly appreciate your support and commitment as we work to improve the reliability of the electrical infrastructure in the area. Please let us know when the construction and outage notices have been delivered to the impacted addresses.
If anyone has any questions or concerns regarding this work or outage, please contact our teams directly as follows:
Thank you,